The contract scope included demolition of Boiler & Hot water piping, installation of new electric duct heaters, replacement of CWSR valves & gages, replacement of condenser water pumps, cooling towers, installation of new split A/C units at MDF rooms, replacement of Fire Alarm system, installation of new site lighting, new clean power receptacles, new CAT6 data outlets and CATV outlets, and replacements of intercom handsets.


Name and Location of Project: Gotha Middle School 9155 Gotha Road Windermere, FL 34786
Market: K-12
Client: Orange County Public Schools
Date Project was Completed: July 2010
Size of Project: 145,000 SF
Cost of Project: $2,197,573
This project was completed by Williams Company, in association with ACY Contractors.